LAS LOMAS, Monterey County — October 30, 2026. Monterey County supervisors voted on September 29, 2026 to authorize an engineering agreement for a sewer repair program in Las Lomas and Pajaro. The work is backed by a $4,075,000 U.S. Department of Agriculture Rural Development grant that the county had accepted in February 2025. The September action advances project design; it is not confirmation that underground repairs have been completed.
What is planned in Las Lomas?
The county's board report identifies approximately 24 spot-repair locations on existing sewer mains in Las Lomas. The project also calls for rebuilding or repairing the aging Pajaro sewer lift station. Both fall under the Pajaro County Sanitation District, which collects sewage and sends it to Watsonville for treatment.
When will construction start?
The county chose the Wallace Group for professional services. Staff estimate $422,000 for design and preconstruction services, planned for completion by July 2027. The public report does not specify a construction commencement date, a finalized street-by-street traffic schedule or a completion deadline for all 24 sites. Residents should watch for notices before assuming excavation is imminent.
Is another grant involved?
County staff describe a separate $1.5 million federal EPA community-grant earmark intended for additional spot repairs in Las Lomas. The report says the related application had been submitted and funding was expected in 2027. That is different from the already awarded $4.075 million USDA grant. Treating the expected EPA money as disbursed funding now would overstate the project's financing.
What should residents ask about?
People living near possible work sites can ask Monterey County Public Works about proposed excavation locations, planned street access, the project design timetable and how later interruptions would be announced. The district covers more than one community, so a repair at the Pajaro lift station should not be described as construction happening in Las Lomas itself.
Official source: Monterey County Board of Supervisors, A 26-405, September 29, 2026, approved engineering agreement and funding report.
Editorial note: The awarded USDA funding, planned Las Lomas repairs and design schedule are drawn from the county's approved record; construction is not reported as underway.
Support Las Lomas News
Choose how to support Las Lomas News:
Credit / Debit Card via StripeChoose your contribution amount on the secure California58 Stripe checkout. One-time support for independent local journalism.
Continue with PayPal Continue with ZelleZelle payments go to Vitaly Ataev Troshin. Please verify the recipient in your bank before sending. Availability depends on your bank.
Optional reader support. When possible, add “Las Lomas News” to the payment note. Contributions are not advertised as tax-deductible. Support does not influence editorial decisions.More from Las Lomas News
- Hall District Elementary in Las Lomas Serves 417 Students; State Says Seven in Ten Are English Learners →
- Las Lomas Included in Monterey County's $27.5 Million Climate Grant Application: Award Not Yet Confirmed →
- Las Lomas' Hall Road Safety Plan Still Seeks Design Funding for Roundabout and Sidewalk Options →
- Las Lomas Drive Bicycle and Pedestrian Project: County Documents $3.47 Million Contract and Safer Walking Routes →
COMMUNITY